Report for July 2016

Report Date
July 2016

Achievements this Period

  • Majority of final migrations completed
  • Project closure drafted and circulated
  • Project closed

Issues

  • None

Next Steps

  • None. Project now closed.
Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
253.0 days
Activity this month
15.0 days
Activity this year
113.0 days
Activity to date
265.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Decommission Obsolete Infrastructure
Code
INF105
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
08-Sep-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2016
Programme Priority
1
Overall Priority
Normal
Category
Compliance