Report for November 2014
- Report Date
- November 2014
Achievements this Period
- Project brief approved by WIS
- Further meetings with business users to determine scope of catalogue and approach to planning
- Further discussions round TSM work
Issues
- Start of cataloguing task delayed (by a week) because of resourcing availability
Next Steps
- Work to commence on cataloguing obsolete elements in infrastructure
- Review of catalogue by project stakeholders
- Planning of next stages of project to be drafted and agreed with stakeholders
Milestones
05-Dec-2014 | Review of catalogue of obsolete infrastructure | Analyse |
12-Dec-2014 | Further planning & estimation of subsequent stages | Analyse |
19-Dec-2014 | Planning (second phase) signed off | Analyse |
27-May-2016 | Final Delivery | Deliver |
01-Jul-2016 | Closure | Close |
- Approved budget
- 253.0 days
- Activity this month
- 7.0 days
- Activity this year
- 14.6 days
- Activity to date
- 14.6 days
- Estimate to complete current year
- 139.0 days
- Estimate to complete future years
- 100.0 days