Report for December 2014

Report Date
December 2014

Achievements this Period

  • Progress with testing and implementation of TSM

Issues

  • Cataloguing task delayed because of resource conflict in Development Technologying availability
  • Replanning milestone rescheduled to January

Next Steps

  • Work on cataloguing obsolete elements in infrastructure to be completed
  • Review of catalogue by project stakeholders
  • Planning of next stages of project to be drafted and agreed with stakeholders

Milestones

15-Jan-201505-Dec-2014Review of catalogue of obsolete infrastructureAnalyseNoeditview
20-Jan-201520-Jan-2015Further planning & estimation of subsequent stagesAnalyseNoeditview
22-Jan-201522-Jan-2015Planning (second phase) signed offAnalyseNoeditview
27-May-201627-May-2016Final DeliveryDeliverNoeditview
01-Jul-201601-Jul-2016ClosureCloseNoeditview

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
253.0 days
Activity this month
7.8 days
Activity this year
23.2 days
Activity to date
23.2 days
Estimate to complete current year
128.0 days
Estimate to complete future years
101.0 days

Project Info

Project
Decommission Obsolete Infrastructure
Code
INF105
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
08-Sep-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2016
Programme Priority
1
Overall Priority
Normal
Category
Compliance