Report for February 2015
- Report Date
- February 2015
Achievements this Period
- TSM established and live in DEV environment
- Work started on setting up TSM in Test environment
- More detail on obsolete servers added to catalogue
- Handover of Password Manager Pro to Production Management started
- Build of replacement SOA DEV environment started
Issues
- JIRAs raised with ITI Unix regarding TSM configuration
Next Steps
- Prioritisation of what is to be decommissioned to be carried out by project team
- TSM to be deployed in TEST & LIVE
- Password Manager deployment to be completed
- Build of SOA DEV environment to be completed
Milestones
05-Mar-2015 | TSM work completed | Build |
02-Apr-2015 | Password Manager work completed | Build |
07-May-2015 | Unix decommissioning (14-15) completed | Build |
25-Jun-2015 | Windows decommissioning (14-15) completed | Build |
02-Nov-2015 | Unix decommissioning (15-16) completed | Build |
16-Nov-2015 | RedHat decommissioning (15-16) completed | Build |
30-Nov-2015 | Recommendations and procedures signed off | Deliver |
07-Dec-2015 | Windows decommissioning (15-16) completed | Build |
17-Dec-2015 | Closure | Close |
- Approved budget
- 253.0 days
- Activity this month
- 23.6 days
- Activity this year
- 67.9 days
- Activity to date
- 67.9 days
- Estimate to complete current year
- 86.2 days
- Estimate to complete future years
- 100.0 days