Report for February 2015

Report Date
February 2015

Achievements this Period

  • TSM established and live in DEV environment
  • Work started on setting up TSM in Test environment
  • More detail on obsolete servers added to catalogue
  • Handover of Password Manager Pro to Production Management started
  • Build of replacement SOA DEV environment started

Issues

  • JIRAs raised with ITI Unix regarding TSM configuration

Next Steps

  • Prioritisation of what is to be decommissioned to be carried out by project team
  • TSM to be deployed in TEST & LIVE
  • Password Manager deployment to be completed
  • Build of SOA DEV environment to be completed

Milestones

 

05-Mar-2015TSM work completedBuild
02-Apr-2015Password Manager work completedBuild
07-May-2015Unix decommissioning (14-15) completedBuild
25-Jun-2015Windows decommissioning (14-15) completedBuild
02-Nov-2015Unix decommissioning (15-16) completedBuild
16-Nov-2015RedHat decommissioning (15-16) completedBuild
30-Nov-2015Recommendations and procedures signed offDeliver
07-Dec-2015Windows decommissioning (15-16) completedBuild
17-Dec-2015ClosureClose

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
253.0 days
Activity this month
23.6 days
Activity this year
67.9 days
Activity to date
67.9 days
Estimate to complete current year
86.2 days
Estimate to complete future years
100.0 days

Project Info

Project
Decommission Obsolete Infrastructure
Code
INF105
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
08-Sep-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2016
Programme Priority
1
Overall Priority
Normal
Category