Report for March 2015

Report Date
March 2015

Achievements this Period

  • TSM established and live in TEST environment
  • Work almost complete on setting up TSM in LIVE environment
  • First batch of obsolete servers (25) powered down and awaiting removal from network
  • Plans on next batch of servers being finalised
  • Work on migration to Password Manager continuing
  • Build of replacement SOA DEV environment completed

Issues

  • Deployment of TSM in LIVE taking longer than anticipated

Next Steps

  • TSM to be deployed in LIVE
  • Password Manager deployment to be completed
  • 'Priority 1' servers to be removed from network
  • 'Priority 2' decommissions to commence

Milestones

 

09-Apr-2015Password Manager work completedBuild
10-Apr-2015TSM work completedBuild
07-May-2015Unix decommissioning (14-15) completedBuild
25-Jun-2015Windows decommissioning (14-15) completedBuild
02-Nov-2015Unix decommissioning (15-16) completedBuild
16-Nov-2015RedHat decommissioning (15-16) completedBuild
30-Nov-2015Recommendations and procedures signed offDeliver
07-Dec-2015Windows decommissioning (15-16) completedBuild
17-Dec-2015ClosureClose

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
253.0 days
Activity this month
29.0 days
Activity this year
98.1 days
Activity to date
98.1 days
Estimate to complete current year
53.9 days
Estimate to complete future years
101.0 days

Project Info

Project
Decommission Obsolete Infrastructure
Code
INF105
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
08-Sep-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2016
Programme Priority
1
Overall Priority
Normal
Category
Compliance