Report for April 2015

Report Date
April 2015

Achievements this Period

  • TSM established and deployed in LIVE environment
  • Plans for next batch of servers finalised
  • Build of replacement SOA DEV environment tested successfully

Issues

  • Deployment of TSM in LIVE taking longer than anticipated
  • Delays to sign off of new SOA DEV environment

Next Steps

  • Password Manager deployment to be completed
  • 'Priority 1' servers to be removed from network
  • 'Priority 2' decommissions to commence
  • Implementation of TSM to be signed off

Milestones

 

07-May-2015Unix decommissioning (14-15) completedBuild
11-May-2015Password Manager work completedBuild
13-May-2015TSM work completedBuild
25-Jun-2015Windows decommissioning (14-15) completedBuild
02-Nov-2015Unix decommissioning (15-16) completedBuild
16-Nov-2015RedHat decommissioning (15-16) completedBuild
30-Nov-2015Recommendations and procedures signed offDeliver
07-Dec-2015Windows decommissioning (15-16) completedBuild
17-Dec-2015ClosureClose

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
253.0 days
Activity this month
14.9 days
Activity this year
115.1 days
Activity to date
115.1 days
Estimate to complete current year
37.9 days
Estimate to complete future years
100.0 days

Project Info

Project
Decommission Obsolete Infrastructure
Code
INF105
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
08-Sep-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2016
Programme Priority
1
Overall Priority
Normal
Category
Compliance