Report for May 2015

Report Date
May 2015

Achievements this Period

  • Implementation of TSM in LIVE signed off
  • Workshops run for Dev Tech/Tech Man colleagues
  • 'Priority 1' servers (Solaris & RedHat) removed from UoE network
  • 'Priority 2' decommissions (Windows) started
  • Decommissions of other servers and 15-16 decommissions planned

Issues

  • None reported 

Next Steps

  • Password Manager deployment to be completed
  • Migration plans for servers outwith the priority 1 & 2 groupings to be finalised

 

Milestones

25-Jun-2015Windows decommissioning (14-15) completedBuild
26-Jun-2015Password Manager work completedBuild
02-Nov-2015Unix decommissioning (15-16) completedBuild
16-Nov-2015RedHat decommissioning (15-16) completedBuild
30-Nov-2015Recommendations and procedures signed offDeliver
07-Dec-2015Windows decommissioning (15-16) completedBuild
17-Dec-2015ClosureClose
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
253.0 days
Activity this month
14.9 days
Activity this year
132.9 days
Activity to date
132.9 days
Estimate to complete current year
21.0 days
Estimate to complete future years
100.0 days

Project Info

Project
Decommission Obsolete Infrastructure
Code
INF105
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
08-Sep-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2016
Programme Priority
1
Overall Priority
Normal
Category
Compliance