This project is to provide a new infrastructure for the application tier, implementing the recommendations of the 13/14 INF104 project. This would be a skeleton framework implemented to support the application tier going forward and to underpin any new developments in the application tier across business areas. This project will only provide the infrastructure and will not include any migrations.

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
January 2015 BLUE 60.0 days 62.0 days 0.0

Project Info

Project
New Application Tier Replacement
Code
INF106
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
Adam Wadee
Project Sponsor
David Smyth
Current Stage
Close
Status
Closed
Start Date
25-Aug-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
06-Feb-2015
Programme Priority
2
Overall Priority
Normal
Category
Compliance