The Division has built up reliance on a number of key products over the years to assist in project and service delivery.

This project would apply relevant upgrades to the following products as required:

JIRA

JIRA Agile

Bamboo

We will look to upgrade to latest stable and supported versions of the products above. This will not review new functionality and only concentrate on software upgrades.

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
June 2015 BLUE 51.0 days 51.0 days 0.0

Project Info

Project
Annual upgrades of development tools (JIRA/Bamboo)
Code
INF109
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
Gillian Henderson
Project Sponsor
Bill Lee
Current Stage
Close
Status
Closed
Start Date
17-Feb-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
25-Jun-2015
Programme Priority
5
Overall Priority
Normal
Category
Compliance