This project will upgrade the ASTA resource and planning software used by IS Applications and Student and Academic Services (SACs). 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
February 2017 BLUE 29.0 days 29.0 days 0.0

Project Info

Project
ASTA Upgrade 15/16
Code
INF116
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Nikki Stuart
Project Sponsor
Rhian Davies
Current Stage
Close
Status
Closed
Start Date
17-Feb-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
03-Mar-2017
Programme Priority
10
Overall Priority
Normal
Category
Compliance

Documentation

Project Dashboard

Project journal

Change dashboard