Disaster Recovery plans have not been reviewed over the last few years. While infrastructure and software components have been delivered with Disaster Recovery thoughts and procedures, there is a lack in having an overarching Disaster Recovery plan.

This project’s focus is to review the University’s priority services managed by IS Applications. The project will establish the set of components which are used by the priority services and establish Disaster Recovery plans for each of the components.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
February 2017 BLUE 42.0 days 35.4 days 0.0

Project Info

Project
Disaster Recovery for Priority Services
Code
INF120
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
05-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
03-Mar-2017
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Project Dashboard

Change dashboard

Nothing to report.