This project would apply relevant upgrades to the following products as required: ASTA Bamboo GIT / Gitlab Python / Django Puppet / Yii We will look to upgrade to latest stable and supported versions of the products above. This will not review new functionality and only concentrate on software upgrades

Not all applications need necessarily but upgraded each year.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2018 GREEN 110.0 days 108.1 days 0.0

Project Info

Project
Annual Upgrade of Development Tools 17-18
Code
INF131
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Richard Bailey
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
04-Dec-2017
Planning Date
02-Feb-2018
Delivery Date
31-Jul-2018
Close Date
10-Aug-2018
Programme Priority
7
Overall Priority
Normal
Category
Compliance

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.