Previously up to 2016, there was no consistent Disaster Recovery review and testing performed for over 10 years.

Significant technical debt in the Disaster Recovery was built up, leaving University priority services at risk in case of major Disasters.

 

This project has two main objectives:

 

  1. Build upon the 2016 Disaster Recovery project (INF120), by picking up recommendations:

  • Review Disaster Recovery documentation location.  
  • Improve documentation related to Disaster Recovery for Top and medium priority services.
  1. Review and update the Disaster Recovery  documentation produced in the 2016 initial Disaster Recovery project.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
June 2019 BLUE 20.0 days 18.9 days 2.9

Project Info

Project
Annual DR Review
Code
INF138
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Ian Mitchell
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
04-Feb-2019
Planning Date
29-Mar-2019
Delivery Date
14-Jun-2019
Close Date
28-Jun-2019
Programme Priority
4
Overall Priority
Normal
Category
Compliance

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.