Monthly Project Report
- Report Date
- July 2019
Achievements
PMP
- PMP has been completed successfully in TEST
- PMP in LIVE will be carried out by Tech Man in August
- At meeting on 17-Jul with Tech Man, Apps Supp and Project Manager agreed PMP in LIVE will be completed in August within support (less than 2 days effort)
Oracle Grid
- Oracle Grid only exists in LIVE and so the TEST Signoff was withdrawn
- Tech Man has successfully completed all the security patches
- Tech Man successfully completed the upgrade in LIVE
- Oracle Grid went Live on 25-July
General
- Overall Acceptance signed off
- Overall Deployment signed off
- Closure completed, reviewed and signed off
- Budget reduced for INF139 to 120 days (from 140 days)
- Project passed to WIS for Closure on 29-July
- Close project
Issues
-
No issues
Next Steps
- No next steps
GREEN RAG status
Milestones
- None
- Approved budget
- 120.0 days
- Activity this month
- 15.0 days
- Activity this year
- 119.0 days
- Activity to date
- 119.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days