Monthly Project Report

Report Date
July 2019

Achievements

PMP

  • PMP has been completed successfully in TEST
  • PMP in LIVE will be carried out by Tech Man in August 
    • At meeting on 17-Jul with Tech Man, Apps Supp and Project Manager agreed PMP in LIVE will be completed in August within support (less than 2 days effort) 

Oracle Grid

  • Oracle Grid only exists in LIVE and so the TEST Signoff was withdrawn
  • Tech Man has successfully completed all the security patches
  • Tech Man successfully completed the upgrade in LIVE
  • Oracle Grid went Live on 25-July

General

  • Overall Acceptance signed off
  • Overall Deployment signed off
  • Closure completed, reviewed and signed off
  • Budget reduced for INF139 to 120 days (from 140 days)
  • Project passed to WIS for Closure on 29-July
  • Close project

Issues

  • No issues

Next Steps

  • No next steps

 

GREEN RAG status

Milestones

  • None
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
Within Tolerance
Overall
Within Tolerance
Has formal escalation taken place?
No
Change Commentary
Budget has been reduced in July
Activity
Approved budget
120.0 days
Activity this month
15.0 days
Activity this year
119.0 days
Activity to date
119.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Annual Upgrades of Development Tools + frameworks 18/19
Code
INF139
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
17-Sep-2018
Planning Date
02-Nov-2018
Delivery Date
25-Jul-2019
Close Date
02-Aug-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance