Report Date RAG Budget Effort Completed Effort to complete
August 2021 RED 0.0 days 546.0 days 4.0
Content
Status
In Progress
Current Stage
Deliver
Start Date
Tuesday, 24 September 2019
Planning Date
Friday, 2 November 2018
Delivery Date
Tuesday, 21 September 2021
Close Date
Friday, 24 September 2021
Project information
Project Code
INF143
Programme
ISG - IS Applications Infrastructure (INF)
Session
21/22
20/21
19/20
18/19
Organisational Unit
Application Development and Operations
Project Management Office (if relevant)
ISG PMO
Responsibility
Applications Development and Operations
Project Category
Compliance
Project Classification
Run
Funding Source
C
Programme Priority
4
Overall Priority