Report for June 2018
- Report Date
- June 2019
Achievements in Last Period
- An Additional 100 days and an extension of the project into the academic year has been approved
- Dev and Test servers for pilot applications have been configured with Puppet
- Maria DB has been installed and configured on the pilot application Dev Environment including encryption at rest
- As the result of SME absence, these milestones were slightly behind of schedule but the time has been recovered during the reporting period
Issues
- None
Next Steps
- PICCL amending Delivery and Closure milestones to reflect uplift in budget and extension into 2019-2020
- Complete Mirroring
- Commence Performance Testing
- Complete Bamboo configuration
- Build the test environments for the remaining services
- Migration of pilot applications to Test servers and commence system testing
Milestones
Stage | Milestone | Due Date | Complete |
---|---|---|---|
Plan | End of Planning | 14-Nov-2018 | Yes |
Analyse | Application Register Complete | 11-Jan-2019 | Yes |
Design | Infrastructure Design Complete | 01-Feb-2019 | Yes |
Build | Acceptance Sign-off | 09-May-2019 | No |
Build | Infrastructure Build Complete | 14-May-2019 | No |
Deliver | Delivery sign-off | 31-Oct-2019 | No |
Close | Project Close | 15-Nov-2019 | No |
- Approved budget
- 100.0 days
- Activity this month
- 4.6 days
- Activity this year
- 61.3 days
- Activity to date
- 61.3 days
- Estimate to complete current year
- 38.7 days
- Estimate to complete future years
- 100.0 days