Report for May 2021
- Report Date
- May 2021
Achievements for this Period
- WebPA move now scheduled for 03/06/21 in agreement with the business.
Issues
- No major issues
Next Steps
- Complete the WebPA move
- Deployment Sign off Review
- Project Closure
Milestones
Phase 2 (Delivery for BLOGS and MGEN) | 21-May-2021 |
Phase 2 DSOR | 28-May-2021 |
Closure | 11-Jun-2021 |
- Approved budget
- 325.0 days
- Activity this month
- 4.6 days
- Activity this year
- 217.3 days
- Activity to date
- 506.1 days
- Estimate to complete current year
- 3.9 days
- Estimate to complete future years
- 0.0 days