Report for May 2021

Report Date
May 2021

Achievements for this Period 

  • WebPA move now scheduled for 03/06/21 in agreement with the business.

Issues

  • No major issues

Next Steps

  • Complete the WebPA move
  • Deployment Sign off Review
  • Project Closure 

 

Milestones

Phase 2 (Delivery for BLOGS and MGEN) 21-May-2021
Phase 2 DSOR 28-May-2021
Closure 11-Jun-2021
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
Project RAG is AMBER due to outstanding actions to be completed (additional Cost and Time).
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
325.0 days
Activity this month
4.6 days
Activity this year
217.3 days
Activity to date
506.1 days
Estimate to complete current year
3.9 days
Estimate to complete future years
0.0 days

Project Info

Project
MySQL Environment Migration
Code
INF143
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Frankie Quinn
Project Sponsor
Suran Perera
Current Stage
Deliver
Status
In Progress
Project Classification
Run
Start Date
24-Sep-2019
Planning Date
02-Nov-2018
Delivery Date
21-Sep-2021
Close Date
24-Sep-2021
Programme Priority
4
Overall Priority
Highest
Category
Compliance

Documentation