An “Encryption of Data at Rest” report was produced by PwC. Within the content, a number of recommendations were made.
The primary recommendation was that the University should continue to progress with the Oracle Advanced Security solution. It was agreed that this supported the intended development of the Enterprise Data Warehouse (EDW) and that a project should be initiated to progress.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
August 2019 | BLUE | 60.0 days | 46.5 days | 0.0 |