Report for May 2021

Report Date
May 2021

 

Achievements

  • Build of DOCS, FEED and APPS completed in DEV
  • Build and migration of all PURE environments completed
  • Migration of DOCS, FEED and APPS in DEV successfully completed
  • Build of DOCS, FEED and APPS completed in TEST
  • Migration of FEED in TEST successfully completed
  • Resourcing and budget for project discussed and clarified with project sponsor and senior management
  • Outstanding milestones for migrations revised because of progress being made

Issues

  • No major issues reported
  • Some issues in APPS migration but these are being worked through

Next Steps

  • Migration of APPS in TEST and LIVE to be completed
  • Migration of DOCS in TEST and LIVE to be completed
  • Migration of FEED in LIVE to be completed

 

Milestones

Stage Milestone Due Date
Build FEED (Service 6) DEV, TEST and LIVE servers Built, configured and Migrations completed 09-Jun-2021
Build DOCS (Service 5) DEV, TEST and LIVE servers Built, configured and Migrations completed 21-Jun-2021
Build APPS (Service 7) DEV, TEST and LIVE servers Built, configured and Migrations completed 21-Jul-2021
Build Service 8 DEV, TEST and LIVE servers Built, configured and Migrations completed 23-Mar-2022
Build Service 9 DEV, TEST and LIVE servers Built, configured and Migrations completed 25-May-2022
Deliver Decommissioning of any servers 10-Jun-2022
Deliver Deployment Sign Off Review(DSOR) 24-Jun-2022
Close Closure 22-Jul-2022
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
450.0 days
Activity this month
59.4 days
Activity this year
264.9 days
Activity to date
264.9 days
Estimate to complete current year
56.4 days
Estimate to complete future years
125.0 days

Project Info

Project
Move Oracle databases to VMs - Phase 2
Code
INF149
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Suran Perera
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
11-Sep-2020
Planning Date
06-Nov-2020
Delivery Date
24-Jun-2022
Close Date
29-Sep-2022
Overall Priority
Highest
Category
Compliance