Report for July 2022

Report Date
July 2022

Achievements

  • Decommissioning tasks under way
  • Outstanding documentation updated

Issues

  • None reported

Next Steps

  • Complete documentation review
  • Complete decommissioning review
  • Close project

 

Milestones

Close Closure 18-Aug-22

 

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
This project is AMBER because of the delay to completing the closure report. This is attributable to a combination of leave and workload across the project team delaying the final closure.
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
Yes
Escalated to
Programme Manager
Activity
Approved budget
605.0 days
Activity this month
9.3 days
Activity this year
273.5 days
Activity to date
612.4 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Move Oracle databases to VMs - Phase 2
Code
INF149
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Suran Perera
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
11-Sep-2020
Planning Date
06-Nov-2020
Delivery Date
24-Jun-2022
Close Date
29-Sep-2022
Overall Priority
Highest
Category
Compliance