Final RAG Report

Report Date
September 2022

Project is now closed

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
635.0 days
Activity this month
7.3 days
Activity this year
21.0 days
Activity to date
634.3 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Move Oracle databases to VMs - Phase 2
Code
INF149
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Suran Perera
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
11-Sep-2020
Planning Date
06-Nov-2020
Delivery Date
24-Jun-2022
Close Date
29-Sep-2022
Overall Priority
Highest
Category
Compliance