This project is required :

  • to upgrade the application software to latest version v14.0.03 (to be confirmed with Elecosoft) 
  • to migrate database to supported SQL database as current infrastructure is out of support
  • to move to a new Windows server as now nearing End of Life in January 2020
  • to complete automated client rollout of new version

Deliverables:

  • Upgrade ASTA Powerproject application in Test and Live
  • Migrate ASTA Timesheet application in Test and Live
  • Update User documentation (as required for new features)
  • Migrate ASTA Powerproject database to new SQL Database on supported infrastructure
  • Build on new Windows Server on supported infrastructure
  • Automated client rollout

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2020 BLUE 100.0 days 36.0 days 0.0

Project Info

Project
ASTA Upgrade
Code
INF153
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Rhian Davies
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
15-Oct-2019
Planning Date
13-Dec-2019
Delivery Date
25-Jun-2020
Close Date
10-Jul-2020
Overall Priority
Normal
Category
Compliance

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.