This project will continue the decommissioning work of the last four years, and remove obsolete infrastructure from our environment to prevent the accumulation of such old kit which creates major difficulties for us when those systems are no longer supportable.

We have often not been aware of some systems going out of support until very close to their de-support date.

By planning for an annual review of the end of life dates for servers and software, we can minimise the risk to systems and business areas by alerting them in advance to impending obsolescence allowing more time to plan for required upgrades or migrations.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
March 2020 BLUE 50.0 days 51.7 days 1.5

Project Info

Project
Annual Infrastructure Rationalisation Decommissioning
Code
INF155
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Mark Downey
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Sep-2019
Planning Date
20-Sep-2019
Delivery Date
03-Apr-2020
Close Date
17-Apr-2020
Overall Priority
Normal
Category
Compliance