The Division has built up reliance on a number of key products over the years to assist in project and service delivery. 

This project would apply relevant upgrades to the following products as required:    Bamboo  GIT  Python / Django  Puppet / Yii  Sentry  Password Manager  Nexus  Talend    We will look to upgrade to latest stable and supported versions of the products above.   This will not review new functionality and only concentrate on software upgrades 

Not all applications need necessarily but upgraded each year. 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
September 2022 GREEN 85.0 days 89.4 days 0.0

Project Info

Project
Annual Upgrade of Development Tools + Frameworks
Code
INF164
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
John Allison
Current Stage
Close
Status
Closed
Start Date
04-Feb-2022
Planning Date
02-Jun-2022
Delivery Date
26-Jul-2022
Close Date
06-Oct-2022
Overall Priority
Normal

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.