Project Brief

Document Sign Off

 

 

Name Project Role Date Signed Off
Suran Perera Project Sponsor 20/04/22
Ailsa Glass Project Manager 19/04/22
David Watters Programme Manager 20/04/22
Mark Lang Business Lead 19/04/22
Chris Cord Senior User 19/04/22
Peter Jackson Development Technology Representative 19/04/22
Andrew Hobden Production Representative 19/04/22*
Billy Wardop Website & Communication Technologies  19/04/22
Ryan McIntosh Service Manager (Web Services)  19/04/22

The Project Brief and Plan were signed off by the Project Team at the Project Meeting held 19/04/22.

*Andrew did not attend the Project Meeting but provided sign off to the documentation at a separate call after the Project Meeting.

 

For guidance on how to complete the Project Brief template, please click here.

For staff in Information Services Group (ISG), please click here for guidance on how to complete the Project Brief following ISG guidelines. 

Project Info

Project
Annual Maria DB Upgrade
Code
INF165
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Ailsa Glass
Project Sponsor
Suran Perera
Current Stage
Close
Status
Closed
Start Date
14-Mar-2022
Planning Date
20-Apr-2022
Delivery Date
05-Sep-2022
Close Date
26-Oct-2022
Overall Priority
Normal