Deployment Checklist

 

Contributors

Role Organisation Name Date Signed Off
Production Management Coordinator (Owner) Production Management Andrew Hobden 25/10/22
Technical Architect Development Technology Peter Jackson 25/10/22
Senior User Technology Management Chris Cord 25/10/22
Project Manager Project Services Ailsa Glass 26/10/22
Programme Manager Project Services Andy Stewart 26/10/22
Project Sponsor Application Service Group Suran Perera 26/10/22

Note that it will be the infrastructure deployment checklist that will be used for this project.

Project Info

Project
Annual Maria DB Upgrade
Code
INF165
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Ailsa Glass
Project Sponsor
Suran Perera
Current Stage
Close
Status
Closed
Start Date
14-Mar-2022
Planning Date
20-Apr-2022
Delivery Date
05-Sep-2022
Close Date
26-Oct-2022
Overall Priority
Normal