Report for May 2017

Report Date
May 2017
  • Achievements this period:
    • Privacy Impact Assessment approved.
    • Regular reports on collected data to the User Services team.  
  • Issues 
    • Sensor devices have  been damaged or stolen from the study room.  
  • Next Steps
    • Complete and sign off project brief (carried over)  
    • Continue to collect data.
    • Agree sensor design for the CRC reading room (carried over)
    • Agree deployment schedule for the CRC reading room (carried over)
  • Milestones:
    • Deploy sensors to shared study area by end of April - complete
    • Deploy sensors to CRC reading room  - TBC
    • Data collection and analysis complete and way forward agreed by end in March 2018
Project Status
RAG Status
Time
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
There is no specific budget identified for this project. Resources on the project are assigned full time to the programme, and CIS have undertaken some basic technical work as business as usual with core funding.
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Main Library IoT Pilot.
Code
IoT002
Programme
Internet of Things (IOT)
Management Office
ISG PMO
Project Manager
Steve Taylor
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Withdrawn
Start Date
01-Mar-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Nov-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary

Documentation