Report for September 2017

Report Date
September 2017

Awaiting closure report and full project closure.

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
RAG Commentary
There is no specific budget identified for this project. Resources on the project are assigned full time to the programme, and CIS have undertaken some basic technical work as business as usual with core funding.
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Main Library IoT Pilot.
Code
IoT002
Programme
Internet of Things (IOT)
Management Office
ISG PMO
Project Manager
Steve Taylor
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Withdrawn
Start Date
01-Mar-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
08-Nov-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary

Documentation