- Report Date
- April 2017
- Achievements this period:
- Scope agreed
- Funding confirmed.
- Core solution design agreed.
- Technical deployment plan agreed
- Issues
- Next Steps
- Detailed technical design agreed.
- Planning complete.
- Continue with technical build
- Milestones:
- Complete planning and identify full list of milestones - end of May 2017
- Build complete 07 July 2017
- Testing and assurance checks completed and signed off - infrastructure ready - 31/07/2017
- Approved budget
- 145.0 days
- Activity this month
- 5.0 days
- Activity this year
- 15.0 days
- Activity to date
- 15.0 days
- Estimate to complete current year
- 130.0 days
- Estimate to complete future years
- 0.0 days