Technical work progressing (note: This has been delayed due to staff absences but Edina are confident that this will not adversely affect our time scales).
Issues
Completion of work has extended by 3 weeks due to year end impact on Edina resources.
Next Steps
Complete technical build
Milestones:
Core planning complete end of May 2017 - complete.
Build complete 07 July 2017 - this has run over and is now due to be complete 11 Aug.
Testing and assurance checks completed and signed off - infrastructure ready - 31/07/2017 - - this has run over and is now due to be complete 18 Aug.