Report for September 2017

Report Date
September 2017
  • Achievements this period:
    • Server build complete.
    • Initial testing complete.  
  • Next Steps
    • Complete & sign off full testing
    • Project closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
145.0 days
Activity this month
5.0 days
Activity this year
15.0 days
Activity to date
15.0 days
Estimate to complete current year
130.0 days
Estimate to complete future years
0.0 days

Project Info

Project
IoT ELK infrastructure
Code
IoT003
Programme
Internet of Things (IOT)
Management Office
ISG PMO
Project Manager
Steve Taylor
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Start Date
20-Jan-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
19-Jan-2018
Programme Priority
2
Overall Priority
Normal
Category
Discretionary

Documentation