Report for July 2018

Report Date
July 2018

Status:

Both workshop reports virtually complete - just final presentation decisions being discussed. Expected to complete within a few days.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
IoT Research Network and Service Deployment
Code
IoT004
Programme
Internet of Things (IOT)
Management Office
ISG PMO
Project Manager
Steve Taylor
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
05-Sep-2017
Planning Date
23-Feb-2018
Delivery Date
21-Sep-2018
Close Date
03-Oct-2018
Overall Priority
Higher
Category
Discretionary

Documentation