Report for August 2018

Report Date
August 2018

Status:

Project Closed

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Change Commentary
There has been a delay with the completion of the post IoT Workshop reports, although these are complete now, and this has resulted in formal project completion being delayed.
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
IoT Research Network and Service Deployment
Code
IoT004
Programme
Internet of Things (IOT)
Management Office
ISG PMO
Project Manager
Steve Taylor
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
05-Sep-2017
Planning Date
23-Feb-2018
Delivery Date
21-Sep-2018
Close Date
03-Oct-2018
Overall Priority
Higher
Category
Discretionary

Documentation