Monitoring IT and Library Business Service Readiness For Start of Term 2017/18 (ISG005) - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
October 2017 BLUE 40.0 days 14.0 days 1.0
Content
Status
Closed
Current Stage
Close
Start Date
Monday, 22 May 2017
Close Date
Friday, 3 November 2017
Project information
Project Code
ISG005
Programme
ISG Portfolio Projects (OTHISG)
Session
17/18
16/17
Organisational Unit
User Services Directorate
Project Management Office (if relevant)
ISG PMO
Project Category
Discretionary
Funding Source
Core
Overall Priority
Higher