Mid August 2017

Report Date
August 2017
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Current RAG status is GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Monitoring IT and Library Business Service Readiness For Start of Term 2017/18 (ISG005)
Code
ISG005
Programme
ISG Portfolio Projects (OTHISG)
Management Office
ISG PMO
Project Manager
Colin Watt
Project Sponsor
Neil Bruce
Current Stage
Close
Status
Closed
Start Date
22-May-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
03-Nov-2017
Overall Priority
Higher
Category
Discretionary