Overview
Background
University of Edinburgh hosts start of term open days for new students joining the University twice a year; September and January. September intake amounts to ca. 10,000 new students from across the world. Professional Services concentrate on the administrative, IT and joining activities to ensure the best experience possible. ISG is responsible for IT Services readiness, new cards, personal IT (Wi-Fi), Library tours, as well as learning and teaching technologies.
Each directorate will be focused on their specific scope to deliver their services.
This document sets out the scope and accountabilities ISG undertake in the preparation for the new academic year. The objective is to ensure ISG has a consistent, repeatable and coordinated process in place.
Scope
The scope of this project covers:
- will deliver a framework to allow the monitoring of collective readiness across Information Services for the start of term.
- will leverage and build upon service-based work already done including the excellent Start of Term Major Incident report that User Services Division has used over the last two years.
- will seek to highlight areas of potential uncertainty or hot spots in terms of resource requirements.
- will seek to build upon and support the excellent work already done around the start of term period, and showcase best practice and lessons learned for future years.
- Will implement lesson learned from the 2018/19 project, these include:
- Improving engagement in areas
- Starting this year’s project earlier in order to influence a number of activities due to the necessarily long lead time on many of them - for example:
- Estates projects which potentially impact on teaching space at the start of session.
- Communications involving web-based or printed media.
- Ensure the engagement with the Weekly Welcome group, by having a representative on the project team.
- Provide improved clarity around out of hours procedures, roles and responsibilities.
- Agree with SLT which KPIs will be measured and how these will be measured.
- Ensure that SLT set the expectation that individuals involved can commit adequate time to attend meetings and provide two-way communication from their areas.
- “Recommendation that clear guidance on out of hours support for the start of session is agreed at SLT level ahead of the next year’s project in order to reduce ambiguity. NB this was raised following the 17/18 project.” Has this happened?
- Develop and agree on an improved approach with Estates to overcome the challenges of the last two years. Early engagement with the ISG Estates Programme Manager, potentially incorporating the Estates PMO in a more meaningful way.
- Increase student involvement in the project.
- Improve comms with welcome week activities.
- Investigate improvements to the EUCLID/Learn feed so that updates to student details appear quicker in Learn
- Ensure various improvements for welcome week are implemented (see Lessons Learned Report 2018/19 for more details).
- Improved measurement on service availability.
- Develop contingency plans to mitigate the impact on students due to infrastructure failure or attack.
- Starting this year’s project earlier in order to influence a number of activities due to the necessarily long lead time on many of them - for example:
Out of Scope
This project does not replace existing activities for the start of session within the ISG Divisions or across the University as a whole.
Any areas of uncertainty will be communicated via the appropriate IS Divisional representative for management within the division (or service, or project as appropriate).
Objectives and Deliverables
No. |
Description |
Priority* |
Owner |
O1 |
To reduce disruption to services as far as possible and to ensure that impacts on users is minimised. |
M |
Gosia Such |
D1a |
Business context for 2019/20 start of semester 1, in particular, any changes in student numbers, business processes, people or systems which may impact on risk. |
M |
Project |
D1b |
Deliver Communications Plan to for start of semester 1 |
M |
Project |
D2a |
Confirmation and visibility of the staff responsible for start of semester 1 readiness in each ISG Division, and staff people needed to deliver support services over the start of term period; this includes out of hours support, and readiness RAG status. |
M |
Project |
D2b |
Confirmation and visibility of the staff responsible for start of semester 1 readiness in associated Business Partner areas e.g. Student Admin, Estates and staff people needed to deliver support services over the start of term period; this includes out of hours support, and readiness RAG status. |
M |
Project |
D3 |
Visibility of planned changes to existing services from Change Management, and from projects in progress with their delivery RAG status. |
M |
Project |
D4 |
Visibility of planned new services required by Start of Semester 1 delivered by projects in progress and their delivery RAG status. |
M |
Project |
D5a |
Risk and dependency management at portfolio level for all ISG projects needed for the start of semester 1. |
M |
Project |
D5b |
Visibility of Risk and dependency management at portfolio level for any USG, Estates projects needed for the start of semester 1. |
M |
Project |
D6 |
Visibility of the IT and Library Business Services needed for the start of semester 1 (based on the Service Catalogue) and their readiness RAG status. |
M |
Project |
D7 |
A single site providing an overview of projects, services, teams, and RAG statuses; this site should be accessible by anyone in IS to assess the position of the start of semester readiness; This will help establish the status of deliverables D2, D3, D4, D6. |
M |
Project |
D8 |
Processes for reviewing the readiness of services, projects and people at least fortnightly during the period June to October 2019. |
M |
Project |
D9 |
Ensuring clarity and effectiveness of the change management process focusing on the rules, process and details of the change control period before and during Start of Semester 1. |
M |
Project |
D10 |
Ensuring measurement and reporting of Start of Semester KPIs with a comparison against the equivalent data for last year. These KPIs will include but is not limited to:
|
M |
Project |
D11 |
Coordinate and deliver activities around Welcome to Edinburgh (Previously known as Welcome Week) in the Library including:
|
M |
Project |
D12 |
Report to SLT Operations Meeting on a monthly basis |
M |
Tim Gray |
D13 |
Develop contingency plans to deal with major service outages:
|
M |
Project/Service Owners |
Benefits
- Improved visibility across ISG and the University promoting awareness of service changes and improvements.
- Improved data on the impact of previous and planned changes to assist in making better decisions during the start of term period.
- Improved student experience.
- Reduction to cost in ISG staff time resolving incidents resulting from service changes.
- Reduction in costs to IS and the University of managing Major Incidents.
- Establish maintain the start of term statistics and information which can be used for future years.
Success Criteria
Supporting the start of semester 1 with improved overall visibility of:
- the readiness of services and any expected issues.
- staff resources required to support start of term activities and services, and their availability.
- improvement in overall satisfaction score.
Project Milestones
Stage | Milestone | Due Date |
---|---|---|
Plan | End of Planning | 03-May-2019 |
Execute | IS Staff Involvement Agreed | 10-May-2019 |
Execute | Tools, Processes and KPIs Agreed | 07-Jun-2019 |
Execute | Established List of Projects, Services, and Teams | 14-Jun-2019 |
Execute | Communications Plan Agreed | 21-Jun-2019 |
Execute | Staff Contact Lists for Start of Term Agreed | 26-Jul-2019 |
Execute | Welcome Week Planning Complete | 09-Aug-2019 |
Execute | Start of Welcome Week (External Milestone) | 09-Sep-2019 |
Execute | Start of Teaching Week 1 (External Milestone) | 16-Sep-2019 |
Execute | Start of Teaching Week 2 (External Milestone) | 23-Sep-2019 |
Execute | Delivery Sign Off Review following Start of Session | 14-Oct-2019 |
Close | Project Closure | 15-Nov-2019 |