Overview

Background

University of Edinburgh hosts start of term open days for new students joining the University twice a year; September and January.  September intake amounts to ca. 10,000 new students from across the world.  Professional Services concentrate on the administrative, IT and joining activities to ensure the best experience possible.  ISG is responsible for IT Services readiness, new cards, personal IT (Wi-Fi), Library tours, as well as learning and teaching technologies.

Each directorate will be focused on their specific scope to deliver their services.

This document sets out the scope and accountabilities ISG undertake in the preparation for the new academic year. The objective is to ensure ISG has a consistent, repeatable and coordinated process in place. 

Scope

The scope of this project covers:

  • will deliver a framework to allow the monitoring of collective readiness across Information Services for the start of term.
  • will leverage and build upon service-based work already done including the excellent Start of Term Major Incident report that User Services Division has used over the last two years.
  • will seek to highlight areas of potential uncertainty or hot spots in terms of resource requirements.
  • will seek to build upon and support the excellent work already done around the start of term period, and showcase best practice and lessons learned for future years.
  • Will implement lesson learned from the 2018/19 project, these include:
  • Improving engagement in areas
    • Starting this year’s project earlier in order to influence a number of activities due to the necessarily long lead time on many of them - for example:
      • Estates projects which potentially impact on teaching space at the start of session.
      • Communications involving web-based or printed media.
    • Ensure the engagement with the Weekly Welcome group, by having a representative on the project team.
    • Provide improved clarity around out of hours procedures, roles and responsibilities.
    • Agree with SLT which KPIs will be measured and how these will be measured.
    • Ensure that SLT set the expectation that individuals involved can commit adequate time to attend meetings and provide two-way communication from their areas.
    • “Recommendation that clear guidance on out of hours support for the start of session is agreed at SLT level ahead of the next year’s project in order to reduce ambiguity. NB this was raised following the 17/18 project.” Has this happened?
    • Develop and agree on an improved approach with Estates to overcome the challenges of the last two years. Early engagement with the ISG Estates Programme Manager, potentially incorporating the Estates PMO in a more meaningful way.
    • Increase student involvement in the project.
    • Improve comms with welcome week activities.
    • Investigate improvements to the EUCLID/Learn feed so that updates to student details appear quicker in Learn
    • Ensure various improvements for welcome week are implemented (see Lessons Learned Report 2018/19 for more details).
    • Improved measurement on service availability.
    • Develop contingency plans to mitigate the impact on students due to infrastructure failure or attack.

Out of Scope

This project does not replace existing activities for the start of session within the ISG Divisions or across the University as a whole.

Any areas of uncertainty will be communicated via the appropriate IS Divisional representative for management within the division (or service, or project as appropriate).

 

Objectives and Deliverables

No.

Description

Priority*

Owner

O1

To reduce disruption to services as far as possible and to ensure that impacts on users is minimised.

M

Gosia Such

D1a

Business context for 2019/20 start of semester 1, in particular, any changes in student numbers, business processes, people or systems which may impact on risk.

M

Project

D1b

Deliver Communications Plan to for start of semester 1

M

Project

D2a

Confirmation and visibility of the staff responsible for start of semester 1 readiness in each ISG Division, and staff people needed to deliver support services over the start of term period; this includes out of hours support, and readiness RAG status.

M

Project

D2b 

Confirmation and visibility of the staff responsible for start of semester 1 readiness in associated Business Partner areas e.g. Student Admin, Estates and staff people needed to deliver support services over the start of term period; this includes out of hours support, and readiness RAG status.

M

Project

D3

Visibility of planned changes to existing services from Change Management, and from projects in progress with their delivery RAG status.

M

Project

D4

Visibility of planned new services required by Start of Semester 1 delivered by projects in progress and their delivery RAG status.

M

Project

D5a

Risk and dependency management at portfolio level for all ISG projects needed for the start of semester 1.

M

Project

D5b

Visibility of Risk and dependency management at portfolio level for any USG, Estates projects needed for the start of semester 1.

M

Project

D6

Visibility of the IT and Library Business Services needed for the start of semester 1 (based on the Service Catalogue) and their readiness RAG status.

M

Project

D7

A single site providing an overview of projects, services, teams, and RAG statuses; this site should be accessible by anyone in IS to assess the position of the start of semester readiness; This will help establish the status of deliverables D2, D3, D4, D6.

M

Project

D8

Processes for reviewing the readiness of services, projects and people at least fortnightly during the period June to October 2019.

M

Project

D9

Ensuring clarity and effectiveness of the change management process focusing on the rules, process and details of the change control period before and during Start of Semester 1.

M

Project

D10

Ensuring measurement and reporting of Start of Semester KPIs with a comparison against the equivalent data for last year. These KPIs will include but is not limited to:

  • Service availability and reliability
  • overall student-facing systems availability over the Start of Semester period
  • usage stats
  • change requests requested and approved during the change control period All these should be compared against last year's data.
  • overall satisfaction score (introduced by IS Change Manager)

M

Project

D11

Coordinate and deliver activities around Welcome to Edinburgh (Previously known as Welcome Week) in the Library including:

  • Financial estimate for all activities
  • Library branding
  • Card Services (including cards distribution in McEwan Hall on Sunday 8th September 2019)
  • Props: Bags, t-shirts, etc
  • Coordination with other University activities contact: Lesley Ross
  • Work strand Lead Shaun Burnett

M

Project

D12

Report to SLT Operations Meeting on a monthly basis

M

Tim Gray

D13

Develop contingency plans to deal with major service outages:

  • Agree services to be covered
  • Develop contingency plans

M

Project/Service Owners

 

Benefits

  • Improved visibility across ISG and the University promoting awareness of service changes and improvements.
  • Improved data on the impact of previous and planned changes to assist in making better decisions during the start of term period.
  • Improved student experience.
  • Reduction to cost in ISG staff time resolving incidents resulting from service changes.
  • Reduction in costs to IS and the University of managing Major Incidents.
  • Establish maintain the start of term statistics and information which can be used for future years.

Success Criteria

Supporting the start of semester 1 with improved overall visibility of:

  • the readiness of services and any expected issues.
  • staff resources required to support start of term activities and services, and their availability.
  • improvement in overall satisfaction score.

Project Milestones

Stage Milestone Due Date
Plan End of Planning 03-May-2019
Execute IS Staff Involvement Agreed 10-May-2019
Execute Tools, Processes and KPIs Agreed 07-Jun-2019
Execute Established List of Projects, Services, and Teams 14-Jun-2019
Execute Communications Plan Agreed 21-Jun-2019
Execute Staff Contact Lists for Start of Term Agreed 26-Jul-2019
Execute Welcome Week Planning Complete 09-Aug-2019
Execute Start of Welcome Week (External Milestone) 09-Sep-2019
Execute Start of Teaching Week 1 (External Milestone) 16-Sep-2019
Execute Start of Teaching Week 2 (External Milestone) 23-Sep-2019
Execute Delivery Sign Off Review following Start of Session 14-Oct-2019
Close Project Closure 15-Nov-2019

Project Info

Project
IT and Library Business Service Readiness for Start of Term 2019/20
Code
ISG017
Programme
ISG Portfolio Projects (OTHISG)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Neil Bruce
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
09-Apr-2019
Planning Date
03-May-2019
Delivery Date
09-Sep-2019
Close Date
13-Dec-2019
Programme Priority
1
Overall Priority
Normal
Category
Discretionary