Current project status

Report Date RAG Budget Effort Completed Effort to complete
December 2019 BLUE 50.0 days 48.0 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Tuesday, 9 April 2019
Planning Date
Friday, 3 May 2019
Delivery Date
Monday, 9 September 2019
Close Date
Friday, 13 December 2019
Project information
Project Code
ISG017
Programme
ISG Portfolio Projects (OTHISG)
Session
20/21
19/20
18/19
Organisational Unit
IS Applications
Project Management Office (if relevant)
ISG PMO
Responsibility
Applications Development and Operations
Project Category
Discretionary
Project Classification
Run
Funding Source
Core
Programme Priority
1
Overall Priority
Normal
Student Impact
Project deliverables will be used by students