Report for October 2019

Report Date
October 2019

Achievements in Last Period

  • All main activity now completed

  • Deployment review completed

  • Closure questionnaire distributed

Issues

  • No issues to report.

Next StepsĀ 

  • Draft and circulate closure report
  • Close project
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
IT and Library Business Service Readiness for Start of Term 2019/20
Code
ISG017
Programme
ISG Portfolio Projects (OTHISG)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Neil Bruce
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
09-Apr-2019
Planning Date
03-May-2019
Delivery Date
09-Sep-2019
Close Date
13-Dec-2019
Programme Priority
1
Overall Priority
Normal
Category
Discretionary