Delivery milestone report for 16/11/20

Report Date
November 2020

Delivery milestone report for 16/11/20

  • Project closure report to be signed off by Project Sponsor
  • Study Space Service Owner agreed (Kevin Haddow, IS Facilities)

 

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
GREEN
RAG Commentary
Funding for the project has still to be confirmed, so this project is Amber.
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Study Spaces Provision Project
Code
ISG019
Programme
ISG Portfolio Projects (OTHISG)
Management Office
Service Excellence PMO
Project Manager
Karen Beggs
Project Sponsor
Jo Craiglee
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
28-Jul-2020
Planning Date
28-Aug-2020
Delivery Date
30-Oct-2020
Close Date
06-Nov-2020
Overall Priority
Higher
Category
Compliance

Documentation