Current project status

Report Date RAG Budget Effort Completed Effort to complete
June 2021 GREEN 75.0 days 5.8 days 65.0
Content
Status
In Progress
Current Stage
Execute
Start Date
Monday, 29 March 2021
Planning Date
Friday, 23 April 2021
Delivery Date
Friday, 5 November 2021
Close Date
Friday, 3 December 2021
Project information
Project Code
ISG020
Programme
ISG Portfolio Projects (OTHISG)
Session
21/22
20/21
Organisational Unit
Application Development and Operations
Project Management Office (if relevant)
ISG PMO
Responsibility
Applications Development and Operations
Project Category
Discretionary
Project Classification
Grow
Project Type
Service Delivery
Project Size
Small
Project Complexity
Simple
Funding Source
Core
Programme Priority
1
Overall Priority
Highest
Student Impact
Project deliverables will be used by students
Specialist Skills
Communications