Report for March 2021

Report Date
March 2021

Achievements this period

  • The project has been initialed
  • Project website created
  • ASTA project management tasks assigned

Issues

  • No issues to report

Next Steps

  • Hold meetings with key stakeholders to kick off project
  • Complete project planning
Project Status
RAG Status
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
75.0 days
Activity this month
1.0 day
Activity this year
1.0 day
Activity to date
1.0 day
Estimate to complete current year
49.0 days
Estimate to complete future years
25.0 days

Project Info

Project
IT and Library Business Service Readiness for Start of Term 2021/22
Code
ISG020
Programme
ISG Portfolio Projects (OTHISG)
Management Office
ISG PMO
Project Manager
Frankie Quinn
Project Sponsor
Neil Bruce
Current Stage
Execute
Status
In Progress
Project Classification
Grow
Start Date
29-Mar-2021
Planning Date
23-Apr-2021
Delivery Date
05-Nov-2021
Close Date
03-Dec-2021
Programme Priority
1
Overall Priority
Highest
Category
Discretionary

Documentation