Report for April 2021

Report Date
April 2021

Achievements this period

  • Project Brief drafted and signed off by WIS
  • Welcome Week and IT Readiness Work-streams initiated
  • Wiki Page, Sharepoint and Teams site Created
  • Initial Meeting with Comms 
  • WiFi supplier meeting taken place to discuss options as part of Welcome Week workstream

Issues

  • No issues to report

Next Steps

  • Populate Wiki pages with projects, applications and services relating to Welcome Week.
  • Establish ITI representative and take forward findings of Wifi supplier meeting
  • Update to SLT on project status
  • Continue with IT readiness and Welcome Week work-stream meetings
  • Establish Communications plan
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
75.0 days
Activity this month
4.7 days
Activity this year
5.8 days
Activity to date
5.8 days
Estimate to complete current year
40.0 days
Estimate to complete future years
25.0 days

Project Info

Project
IT and Library Business Service Readiness for Start of Term 2021/22
Code
ISG020
Programme
ISG Portfolio Projects (OTHISG)
Management Office
ISG PMO
Project Manager
Frankie Quinn
Project Sponsor
Neil Bruce
Current Stage
Execute
Status
In Progress
Project Classification
Grow
Start Date
29-Mar-2021
Planning Date
23-Apr-2021
Delivery Date
05-Nov-2021
Close Date
03-Dec-2021
Programme Priority
1
Overall Priority
Highest
Category
Discretionary

Documentation