Report for May 2021

Report Date
May 2021

Achievements this period

  • A paper detailing how this year's project will be delivered was written for IT Committee and Knowledge Strategy Committee. The paper was presented at both committees  and well received.
  • IT Readiness strand is up and running with bi-weekly meetings.
  • Welcome Week strand is up and running with bu-weekly meetings.
  • Presentation given to ISG SLT.

Issues

  • At the outset of the project, the 14 projects/activities identified by CIO for start of term, were to be programme managed by a programme manager from Strategic Change Team. It emerged during this reporting period that this is no longer the case. The programme management for these project is a significant amount of work, as information about many of these project/initiatives is unknown. This programme management will be picked up by the senior PM on this project.
  • No progress has been made regarding discussions with ITI about WiFi connectivity for students arriving in Edinburgh for the first time. The project sponsor will take this forward. 

Next Steps

  • Continue with IT Readiness monitoring and reporting.
  • Continue with Welcome Week planning.
  • Present to ISG SLT at the projects meeting in June

RAG Commentary

  • The project is reporting as GREEN for May 20201.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
75.0 days
Activity this month
4.7 days
Activity this year
5.8 days
Activity to date
5.8 days
Estimate to complete current year
40.0 days
Estimate to complete future years
25.0 days

Project Info

Project
IT and Library Business Service Readiness for Start of Term 2021/22
Code
ISG020
Programme
ISG Portfolio Projects (OTHISG)
Management Office
ISG PMO
Project Manager
Frankie Quinn
Project Sponsor
Neil Bruce
Current Stage
Execute
Status
In Progress
Project Classification
Grow
Start Date
29-Mar-2021
Planning Date
23-Apr-2021
Delivery Date
05-Nov-2021
Close Date
03-Dec-2021
Programme Priority
1
Overall Priority
Highest
Category
Discretionary