Report for July 2023

Report Date
July 2023

Achievements this period

  • IT Readiness meetings continue on track, the meeting frequency now weekly. 
  • Welcome Week Planning continues 
    • Web and Comms - work progressing, see issue below regarding MFA.
    • Purchasing - Requisition/Purchase Orders completed, waiting delivery of various items in August.
    • Social Media - planning continues.
    • Content creation - planned and progressing well.
    • Experiential
      • Piper confirmed for International arrivals weekend
      • Array of prizes for various experiential activities agreed/procured. 

Issues

  • It has been decided that new students will not automatically be enrolled into MFA for Office 365. How this will impact comms has tp be clarified in early August. 
  • There is a threat of strike action during Welcome Week. This is noted in the project risk log Impact of Strike Action during Welcome Week. If strike action is widespread we may not be in a position to fully implement our welcome week plans. A decision by Unison will be made in July, when the outcome is known contingency plans will be drawn up by the project manager.  
  • The food in AH meant that access to creative tools (Adobe/DaVinci Resolve has been limited. This has now been solved with the deliver of an iMac from AH to our project assistant. 

Next Steps

  • Continue with Welcome Week preparations across all work-streams.
  • Continue to monitor IT Readiness across ISG.
  • Finalise comms with the MFA project team after a decision is made on the rollout.
  • Complete internal procurements.
  • Floor plan walkthrough.
  • PM to present at Section Heads Meeting in early August.
  • Create contingency plans in the event that potential strike action occurs.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
40.0 days
Activity this month
2.5 days
Activity this year
17.5 days
Activity to date
17.5 days
Estimate to complete current year
17.0 days
Estimate to complete future years
30.0 days

Project Info

Project
IT & Library Business Service Readiness for Start of Semester 23/24
Code
ISG026
Programme
ISG User Services (USD)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Gosia Such
Current Stage
Close
Status
Closed
Start Date
19-Jan-2023
Planning Date
09-Mar-2023
Delivery Date
09-Sep-2023
Close Date
12-Dec-2023
Overall Priority
Normal

Documentation