The Information Services Group website is hosted on the University's Drupal 7-based CMS EdWeb. Drupal 7 is reaching its end of life in November 2023 and all content needs to be migrated over to a new Drupal 9 web publishing platform, ideally by April 2023. This project will deliver the migration of the Information Services Group webpages from EdWeb to the new Web-publishing platform. The project will focus preparing the current content prior to a lift and drop migration to the new platform. This project will not redesign or restructure the website.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
October 2024 GREEN 55.0 days 53.1 days 12.4

Project Info

Project
ISG Website Migration
Code
ISG027
Programme
ISG User Services (USD)
Management Office
ISG PMO
Project Manager
Anna Forostianko
Project Sponsor
Shaun Burnett
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
06-Oct-2022
Planning Date
11-Nov-2022
Delivery Date
11-Nov-2024
Close Date
27-Nov-2024
Programme Priority
2
Overall Priority
Higher
Category
Compliance

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.