Current project status

Report Date RAG Budget Effort Completed Effort to complete
November 2015 BLUE 185.0 days 53.0 days 110.0
Content
Status
Closed
Current Stage
Close
Start Date
Tuesday, 30 June 2015
Close Date
Saturday, 31 December 2016
Project information
Project Code
ITI000
Programme
ITI - Divisional and Directorate (IDR)
Session
16/17
15/16
Organisational Unit
Others