November 2015
- Report Date
- November 2015
The first four months of the work has been focussed on annual planning and increasing visibility of the ITI work via projects planned, showing on the SMT sheet and set up on the projects website. This is mostly in place.
2016 will see emphasis on establishing the methodology, ensuring websites are maintained, providing guidances to PM's via more guides, hands-on, further training and awareness sessions.
Achievements in Last Period
- number of projects declared on SMT as annual planning completed
- number of annual planning projects on the projects website around 70%
- second project manager training done
Issues and Risks
- none
Next Steps
- all projects started up to December must be on projects website
- all projects that have started must have project brief, milestones, risks, issues and project report
- follow up with Sharepoint training
- Reconcile Roadmap expenditure with planned projects
- start up INV003 and DTP001 projects for January end
- review impact on work from INF and MVM programmes
- create an ITI forward look if Tony Approves
- Approved budget
- 185.0 days
- Activity this month
- 21.0 days
- Activity this year
- 53.0 days
- Activity to date
- 53.0 days
- Estimate to complete current year
- 110.0 days
- Estimate to complete future years
- 0.0 days