Report for March 2018

Report Date
March 2018

Achievements

  • Explored patching the RedHat Apache httpd sources to integrate  mod_md
  • Became active in the Inline with Upstream Stable project which was identified as the best route to a sustainable patched Apache RPM.
  • Extended operational duties to cover general team service desk activities
  • Completed our Data Center induction process

Next Steps

  • Become familiar with the University's Citrix Netscaler load balancer
  • Investigate Nginx usage across the University
  • Partial break for exam season

Budget Information

  • Spend to date £1,525
  • Estimated spend £4,580
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
56.0 days
Activity this month
8.0 days
Activity this year
16.0 days
Activity to date
16.0 days
Estimate to complete current year
40.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Free Automatic Website Certificates
Code
ITI029
Programme
IS Innovation - IT Infrastructure (INI)
Management Office
ISG PMO
Project Manager
Kenneth MacDonald
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Start Date
27-Oct-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2018
Overall Priority
Normal

Documentation