Report for May 2018

Report Date
May 2018

Achievements

  • Identified a design for managing certificates on our Citrix Netscaler load balancer
  • Surveyed Nginx usage across the University - very little
  • Drafted project report
  • Partial break for exam season
  • Extended operational duties to cover general team service desk activities
  • Performed data analysis on our mail relay static tables

Next Steps

  • Implement design for the University's Citrix Netscaler load balancer on a development installation
  • Final report

Budget Information

  • Spend to date £1,525
  • Estimated spend £4,580
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
56.0 days
Activity this month
20.0 days
Activity this year
36.0 days
Activity to date
36.0 days
Estimate to complete current year
20.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Free Automatic Website Certificates
Code
ITI029
Programme
IS Innovation - IT Infrastructure (INI)
Management Office
ISG PMO
Project Manager
Kenneth MacDonald
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Start Date
27-Oct-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2018
Overall Priority
Normal