Report for August
- Report Date
- August 2012
Achievements in Last Period
During the month, work has been on-going with roll-out in phase 3
With regards phase 3 (Schools without computing officers) (i) The rollout has continued during this month (ii) The current status can be viewed on the wiki (iii) The latest details from the wiki can be summarised as follows (iv) USD have advised that any remaining pc's after mid-September will be dealt with by IS helpline
College / School | Total pcs identified | Total pcs identified last month | Total pcs updated | Total last month | Remaining pcs to be scheduled | Remaining pcs to be scheduledlast month |
HSS | ||||||
Divinity | 75 | 75 | 75 | 75 | 0 | 0 |
Health in Social Sciences | 50 | 50 | 45 | 38 | 5 | 12 |
History, Classics and Archaeology | 89 | 91 | 84 | 67 | 5 | 22 |
LLC Confucius Institute | 12 | 12 | 12 | 11 | 0 | 1 |
School of Education | 139 | 130 | 77 | 43 | 63 | 87 |
OLL | 42 | 42 | 41 | 41 | 1 | 1 |
MVM | ||||||
Central | 87 | 87 | 62 | 62 | 25 | 25 |
Little France | 208 | 84 | 84 | 20 | 124 | 64 |
Western General | 60 | 55 | 50 | 23 | 10 | 32 |
CSE | ||||||
College Office | 35 | 35 | 35 | 35 | 0 | 0 |
Centre for Science at Extreme Conditions | to be confirmed |
Issues
None
Next Steps
Closure meeting is scheduled for 13th September
Target date | Title |
---|---|
13-Sep-2012 | Closure |
- Approved budget
- 25.0 days
- Activity this month
- 1.0 day
- Activity this year
- 1.0 day
- Activity to date
- 19.1 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days